Lower temperatures aren’t the only changes fall has brought to Delta. This 30-second slideshow has us feeling nostalgic as we look back over the last 10 months and see how much the front of the Delta Middle School addition has changed!
As much as the exterior has changed over time, the biggest developments of the last two months are happening inside the building. Remember this 360-image from the first of November, 2018? It’s the cafeteria.
Post from RICOH THETA. – Spherical Image – RICOH THETA
Now check out this shot of the cafeteria, taken from the same spot 11 months later!
Post from RICOH THETA. – Spherical Image – RICOH THETA
Aside from concrete slabs, walls, and windows, here’s a list of a few other things that have been added:
– all the mechanical (HVAC) is roughed in;
– all the plumbing is roughed in;
– the electrical rough-in is nearly complete;
– drywall is installed, taped, and textured;
– walls are being painted;
– parking lot has been poured and nearly all of the sidewalks.
Up next: acoustical ceiling tiles, flooring, door installation, and other finishes that are going to make the middle school an educational bastion.