Going Vertical

Going Vertical

Last week, structural steel columns were placed, and the insulated concrete forms (ICF) started going up to demarcate walls. Now it’s much easier to visualize the layout of the middle school addition. In the image above, the architectural drawing overlays an...
Progressing with Pours

Progressing with Pours

Today’s slab pour came in at 80 yards — the biggest pour for the Delta Middle School addition to date. Rise and shine! It’s a great day for a pour. The last slab pour is scheduled for Friday, 1/11. Getting these slabs poured may seem like a long time...
Baby, It’s Cold Outside

Baby, It’s Cold Outside

While middle schoolers are enjoying their last week of winter break, KGCI continues to push forward with the building addition…in spite of the cold temperatures.  Rebar is placed at the site of the next slab pour. The cold affects the planned concrete pours...