by kissnergc | Feb 12, 2019 | Commercial Projects, Projects
Over the last couple of weeks, the Nudura ICF have continued going up at Delta Middle School, with many walls reaching an elevation of approximately 14 feet. Concrete is pumped into the ICF. With the walls up that far on the north, east, and west sides, Rocky Mountain...
by kissnergc | Jan 25, 2019 | Commercial Projects, Projects
Here’s a history lesson and a construction update for you. Academics befit a school building project, so here goes. Ever wonder where the idiom “beyond the pale” came from? Or what it means for that matter? And (cough cough) what it has to do with...
by kissnergc | Jan 21, 2019 | Commercial Projects, Projects
Last week, structural steel columns were placed, and the insulated concrete forms (ICF) started going up to demarcate walls. Now it’s much easier to visualize the layout of the middle school addition. In the image above, the architectural drawing overlays an...
by kissnergc | Jan 8, 2019 | Commercial Projects, Projects
Today’s slab pour came in at 80 yards — the biggest pour for the Delta Middle School addition to date. Rise and shine! It’s a great day for a pour. The last slab pour is scheduled for Friday, 1/11. Getting these slabs poured may seem like a long time...
by kissnergc | Jan 2, 2019 | Commercial Projects
While middle schoolers are enjoying their last week of winter break, KGCI continues to push forward with the building addition…in spite of the cold temperatures. Rebar is placed at the site of the next slab pour. The cold affects the planned concrete pours...